To provide connectivity to the White River Innovation District (former GM Stamping Plant) and in the surrounding neighborhoods, construction is underway on the west side of the White River. This portion of the project is funded by the Indiana Economic Development Corporation and the City of Indianapolis.

Project Scope

Garmong Construction began work in early 2024 to:

  • Reconstruct the “D Loop” from Washington Street to South White River Parkway
  • Relocate South White River Parkway to the west, eventually connecting to the D Loop and Oliver Street at Drover Street
  • Extend Henry Street from Harding Street to the White River
  • Construct Holly Avenue to connect Oliver Street to the new Henry Street

In addition, utility companies are completing work to facilitate the development of the site.

Current Site Aerial

An aerial view of the Elanco development on the west side of the White River, October 2024